I know what you’re thinking, “Another great title by Glen.” I couldn’t resist. Here’s some pictures of the work being done to put us legal so we can place this business on the market.

 

DSC_1029
This is the hole that Leroy did and then gave up. He won’t come back or return my calls. He’s a hack.
Leroy placed the one tank he ordered in the hole that  he dug by Andy's house. Andy's house was to be done second.
Leroy placed the one tank he ordered in the hole that he dug by Andy’s house. Andy’s house was to be done second. You can see the difference between what he did and what the current company was able to accomplish. The hole in front of the tank is where the tank will be placed allowing proper flow to the field.
The hole again. This hole has about 3 to 4 feet of solid rock below the soil.
The hole again. This hole has about 3 to 4 feet of solid rock below the soil. This hole was easier to dig than Tori’s hole. (I know that sounds wrong, but it’s all I got.)
A distant shot of Andy's construction.
A distant shot of Andy’s construction.
This is Tori's hole and they scraped 4 feet of bedrock out of there about an inch at a time.
This is Tori’s hole and they scraped 4 feet of bedrock out of there about an inch at a time.
A close up of the hole by Tori's house.
A close up of the hole by Tori’s house.
They are stockpiling dirt to use as a mounding system for the septic field.
They are stockpiling dirt to use as a mounding system for the septic field.
They are taking the dirt from an old reservoir  that is on the back of the property.
They are taking the dirt from an old reservoir that is on the back of the property.
I was afraid that I would have to actually buy dirt to build the mounds for the 2 systems, but it turns out that the berm that held the water should be enough for this project.
I was afraid that I would have to actually buy dirt to build the mounds for the 2 systems, but it turns out that the berm that held the water should be enough for this project.
In fact there might be enough for the 3rd system I have to do, for the store.
In fact there might be enough for the 3rd system I have to do, for the store.
Some of the chunks of bedrock that they hauled out of the hole at Andy's. Some were about the size of a small car.
Some of the chunks of bedrock that they hauled out of the hole at Andy’s. Some were about the size of a small car.